Using Who Does What When report in MS Project 2010
I'm trying to understand the hours that this report generates. Filtering the actual Project schedule to December 4th for instance I see that my welders have 10 hours of remaining work. When I run the Who Does What When report it shows that the welders have 20.42 hours remaining work. I can't seem to get the remaining work on the schedule to match the hours shown on the WDWW report. So I don't really trust the WDWW report. What is the correct way to run the report so that I generate an accurate daily or weekly shop load? Ultimately I need to be able to know how many craftsmen we need on a certain day in order to complete the scheduled work.
|