Hi I have a question regarding EVA % completed.
It seems that MS projects does not calculate the % complete in EVA after status date. For example, a task with duration 5 days starting on Monday and total budgeted costs of $500 (100 per day). It is Wednesday and I completed 100% but the earned value shows EV = $ 300.


Can someone please explain why MS projects does not calculate the % work completed after status date? Is this how EV works or is there a way in MS projects to show the actual earned value ?
Reply With Quote
  #2  
Old 10-31-2017, 06:35 PM
Mwahaha Mwahaha is offline EVM calculate % completed after status date Windows 10 EVM calculate % completed after status date Office 2016
Novice
 
Join Date: Oct 2017
Posts: 1
Mwahaha is on a distinguished road
Default

Quote:
Originally Posted by kevenang View Post
Hi I have a question regarding EVA % completed.
It seems that MS projects does not calculate the % complete in EVA after status date. For example, a task with duration 5 days starting on Monday and total budgeted costs of $500 (100 per day). It is Wednesday and I completed 100% but the earned value shows EV = $ 300.
Can someone please explain why MS projects does not calculate the % work completed after status date? Is this how EV works or is there a way in MS projects to show the actual earned value ?
u need to set the actual finish date for that task
Reply With Quote
  #3  
Old 11-17-2017, 06:06 PM
Guloluseus Guloluseus is offline EVM calculate % completed after status date Windows 7 64bit EVM calculate % completed after status date Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

Reading your ost, are you entering actual costs in project as well as your budget cost? If you are only putting in the completion date and marking as complete, project will calculate on your resourcing. If the original was set for 100/day and it actually took 3 days, project will take a value of 100/day to give a total of 300, so its working correctly.
EVA is a comparison of actual against budget cost, so it is usually behind as actual costs are not always calculable immediately the task is complete (in my work, at least).
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
EVM calculate % completed after status date Status Date in a Report ebilbrough Project 3 03-09-2017 09:45 AM
calculate date if date entered in cell, do nothing if blank ConfuddledOne Excel 3 11-07-2014 09:37 AM
EVM calculate % completed after status date Count how many have completed each Training Course within a Date Range dmcmillion Excel 3 10-20-2014 09:59 AM
EVM calculate % completed after status date Meaning of current date vs status date when saving baselines ketanco Project 1 02-08-2012 02:20 PM
updating status date and actual duration ketanco Project 5 01-27-2012 07:32 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:53 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft