Midnight_lightning Midnight_lightning is offline How to Track Actual Time Spent Against Plan Windows 10 How to Track Actual Time Spent Against Plan Office 2016
Novice
How to Track Actual Time Spent Against Plan
 
Join Date: Oct 2017
Posts: 1
Midnight_lightning is on a distinguished road
Default How to Track Actual Time Spent Against Plan

Hi,

I have been struggling to answer this for a while, be grateful for some help.

Basically I have a plan with tasks and want to be able to manually key in the amount of time that a resource works on a task so that I can produce a burn-up graph showing whether the project is delivering against effort(work) as well as deadline.

For example. Task A is planned to take 5 days work over 10 days duration but it completes in 8 days using 6 days work.



Any suggestions as to the best way to achieve this would be welcome?

Thanks
Jon
Attached Images
File Type: png Capture.PNG (9.5 KB, 19 views)
Reply With Quote
  #2  
Old 01-08-2018, 03:21 PM
Smalltown61864 Smalltown61864 is offline How to Track Actual Time Spent Against Plan Windows 10 How to Track Actual Time Spent Against Plan Office 2016
Novice
 
Join Date: Jan 2018
Location: Illinois
Posts: 2
Smalltown61864 is on a distinguished road
Default

following this, as I have similar needs for the projects we're working on.
Reply With Quote
  #3  
Old 01-14-2018, 05:33 PM
Guloluseus Guloluseus is offline How to Track Actual Time Spent Against Plan Windows 7 64bit How to Track Actual Time Spent Against Plan Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

as a simple approach, you could use a baseline to get the info directly from the programe. Failing that (and possibly a better choice if tasks vary over time, eg more added or some deleted) use project compare. Once you have that you can take actual against budget work, and plot in excel.
There are better and/or easier ways, but it really depends on how much task variance there is likely to be, and how it was set up initially.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to Track Actual Time Spent Against Plan Eliminate time stamp in Track Changes Aden Word 19 07-10-2023 09:02 PM
How to Track Actual Time Spent Against Plan Track Changes doesn't track Change Case changes wardw Word 3 10-28-2012 05:31 PM
How to Track Actual Time Spent Against Plan Track time that an email was moved to another folder georgiosr Outlook 1 07-21-2012 11:51 AM
Can't change period when adjusting actual time in Web Access chip_saffire Project 0 10-04-2011 12:05 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:36 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft