Same Schedule, but different leveling
 
Join Date: Sep 2017
Posts: 1
stahleen17 is on a distinguished road
Default Same Schedule, but different leveling

Hi,

I have here two sets of a project schedule. The schedules are exactly the same however, one have the Task 1 constraint as "As soon as possible" while the other one set as "Start no earlier than". The duration is the same for both file but I am confused on why MS Project would give me two different resource leveling just because of the constraint on my first task. Any idea why? Thanks.
Attached Files
File Type: mpp Sample B.mpp (273.0 KB, 7 views)
File Type: mpp Sample A.mpp (272.5 KB, 7 views)
Reply With Quote
  #2  
Old 10-01-2017, 04:49 PM
Guloluseus Guloluseus is offline Same Schedule, but different leveling Windows 7 64bit Same Schedule, but different leveling Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

there are a few things that appear to be making this happen.
The first is that tasks 3-6 have no predecessors. as such, they are all happy to start at the same time unless something tells them otherwise- for this, resource levelling is the key item as it will not let one task using founds (for example) start if resources are not available (as you know).
second problem is that you have actual progress plotted which doesnt look right (task 4). this telling project that you have not started task a, but work on B has been partially completed. as such, you are showing progress in the future. If this was the case then the status date would need to be after the partial completion of task b, which would mean that task A must be complete. To cure this, either set the status date to reflect the progress in task 4, or remove the % completion.
in sample A, the start date for task 3 is earlier than sample B - you need to set a constant date for the programme (in project information)or if will push task A back so it it complete before task b, unless you have a "SNET" constraint, which forces the task to split as the actual progress, or % complete, in task 4 will fix the work.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Same Schedule, but different leveling Problem leveling Charli Project 7 02-14-2017 04:54 AM
Same Schedule, but different leveling Leveling Resources Help! Mthomas88 Project 1 09-25-2015 08:25 AM
Same Schedule, but different leveling problem with leveling r77 Project 5 09-17-2015 05:04 AM
Same Schedule, but different leveling Certain Resources Not Leveling PDX-ADM-TRM01 Project 1 04-27-2015 03:45 PM
Question about leveling a project..... sssb2000 Project 3 02-05-2015 12:11 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:41 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft