Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 09-01-2017, 07:27 PM
smachin1000 smachin1000 is offline Resource leveling part time resource Windows 7 64bit Resource leveling part time resource Office 2007
Novice
Resource leveling part time resource
 
Join Date: Sep 2017
Posts: 2
smachin1000 is on a distinguished road
Default Resource leveling part time resource

I'm using Project 2007 and I am working on a project plan where I have a resource available 1.5 hrs / day (so have set their "max. units" at 12.5% to represent this). Some of the tasks in the plan are over 1.5 hrs however (e.g. 3hrs), so when I try to do automatic resource leveling Project complains that 3hrs is > 1.5hrs and won't do it. What I want it to do is realize that the 3hr task will take two 1.5 hr days. I don't want to artificially break down 3hr tasks into two 1.5hr tasks either.

How do I get resource leveling to work like this?
Reply With Quote
  #2  
Old 09-05-2017, 12:00 AM
Guloluseus Guloluseus is offline Resource leveling part time resource Windows 7 64bit Resource leveling part time resource Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

Max units isnt really the way to do this. set up a calendar that allows 1.5hrs/ day and apply it to your resource, and that should cure the problem.
The difference is that max units is not a true limit- you can have a situation where your actual units are greater, whereas with a calendar it is not possible to work outside of the assigned limits.
hope that helps.
Reply With Quote
  #3  
Old 09-07-2017, 06:45 AM
smachin1000 smachin1000 is offline Resource leveling part time resource Windows 7 64bit Resource leveling part time resource Office 2007
Novice
Resource leveling part time resource
 
Join Date: Sep 2017
Posts: 2
smachin1000 is on a distinguished road
Default PT resource

Thanks, custom calendar worked great.
Reply With Quote
Reply

Tags
levelling



Similar Threads
Thread Thread Starter Forum Replies Last Post
Leveling resource not resolving issues Mattias Project 5 02-14-2017 04:26 PM
Resource leveling part time resource How do you shut off/ignore resource leveling pmgreen Project 1 08-22-2014 06:54 AM
Next to the resource bar Part-time% BuffLouis Project 3 08-18-2014 06:05 AM
Resource leveling part time resource Part Time Resource Query iamthequinn Project 1 02-06-2012 08:15 AM
Resource leveling part time resource resource leveling in ms project ketanco Project 1 12-24-2011 12:58 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:57 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft