Make Weekends Working, but keep the columns colour different
I wish to make weekend working, but still show Saturdays and Sundays highlighted columns different from the rest in 2016 Microsoft Project. |
#2
|
|||
|
|||
easiest way is just to set up the calender for every task as 7 day, and keep standard as the default. this will show weekends shaded, but keeps you on 7 day working.
Project itself will not let you shade days unless they are non working, so its probably the only way of doing it as far as I know. hope thats useful |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Creating colour coded columns and auto-generete statistic in separate sheet | krigre | Excel | 1 | 06-10-2015 04:30 AM |
Long, 3 Column Table - Can I make Fit Into Page Columns? | Rigwald | Word Tables | 9 | 08-07-2012 08:14 PM |
How to make two independent columns not using fields and tables | Macieto | Word | 4 | 09-14-2011 04:53 AM |
Recurring tasks falling on weekends - programme for working day prior | guyc | Project | 3 | 09-26-2010 03:32 PM |