Mdon1 Mdon1 is offline Locking number of days in a project Windows 10 Locking number of days in a project Office 2016
Novice
Locking number of days in a project
 
Join Date: Jun 2017
Posts: 1
Mdon1 is on a distinguished road
Default Locking number of days in a project

Hi all

I have a project lasting 140 days (140 days worth of work) however as each activity doesn't start at the end of the previous activity, in that there may be a 3 week gap between activity 1 and activity 2, the actual 'gap' between start and end data is more like 200 days....

Is there a way to lock the 140 days of activity while having the ability to flex the gap between activities, without causing the project length to change (lengthen).

Thank you in advance.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Locking number of days in a project Project does not distribute work evenly between the days Campelliann Project 1 01-09-2017 06:01 PM
Project Calendar - working days have varying hours BarryB Project 1 11-30-2016 07:36 AM
Locking number of days in a project My project plan keeps locking up -not responding JaneG Project 3 10-11-2014 09:38 AM
Locking number of days in a project Formula To Calculate Countdown Days To Project Completion Catherine Project 1 02-19-2014 11:15 AM
Project Days mah_dahshan Project 1 12-17-2012 04:27 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:38 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft