#1
|
|||
|
|||
Hi, I need to help. I want to add 2 column, 1 is Duration 2 is Finish
1. For "Duration" must be: 26751/3600=7.43 day and with formula roundup. result 7.43 to 8 day. 2. For "Finish" must be: start(31.05.2017)+8day=08.06.2017 (saturday workday) |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
showing months in another duration column | ketanco | Project | 8 | 01-20-2015 07:27 AM |
Inconsistent Duration column for the same date ranges | ravl13 | Project | 3 | 07-28-2014 05:16 PM |
start and finish dates exceeding duration | joday48 | Project | 0 | 06-27-2012 04:55 AM |
remaining duration vs finish date | ketanco | Project | 3 | 02-17-2012 02:24 PM |
duration vs actual start and finish dates | ketanco | Project | 1 | 12-14-2011 09:06 AM |