Dear all,
I am having a random issue with a chart while creating a custom report. Currently I am creating a 'Master project plan' which incorporates a number of individual subproject in one place and from those trying to create a master project dashboard/overview report.

I have added a horizontal bar chart to detail each project along with the project duration & % complete details. I've formatted the horizontal axis to detail the date, but this is where my issue lies.
The project dates are set as following:
Start date = 30/01/17
Finish date = 29/05/17
When the data is entered into the chart the axis is stating dates from 30/12/1899 to 09/04/1900.
Does anyone know how I can amend the axis to detail the actual start and finish dates of the specific projects?

Minesh
Attached Images
File Type: png Capture.PNG (13.8 KB, 18 views)
Reply With Quote
  #2  
Old 05-05-2017, 02:56 PM
JulieS JulieS is offline Project 2013 Report Windows 10 Project 2013 Report Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Is Project 2013 fully patched and up to date? Can you edit the timescale? Select the chart and in the Field list panel to the right, select Time. Click Edit. There is a start and finish date. However, the date range in Project is only from 1/1/1984 through Dec 31 2149.

Something is quite wrong.
Reply With Quote
  #3  
Old 05-30-2017, 10:48 AM
mbosi mbosi is offline Project 2013 Report Windows 7 64bit Project 2013 Report Office 2016
Novice
 
Join Date: May 2017
Posts: 1
mbosi is on a distinguished road
Default

I am having this same issue. This is the second time it has happened where the report seems to have disappeared giving me a blank result. This is not an OOB reeport, it is a custom report we created. We have already re-created it once. Any advice on what happened? It was simply a table showing task progress.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Project 2013 Report MS Project 2013 - Overview report error Imagios Project 15 02-05-2016 09:21 AM
Project 2013 Report Newbie q - Create a filter for report in ms project 2013 task due in 2 weeks bypm Project 7 07-10-2015 06:19 AM
Project 2013 Report MS Project 2010 - 'Who Does What When' report question jrdunn78hawk Project 5 06-24-2014 07:00 AM
Project 2013 Report Sub-Project and resource report codeghi Project 16 04-26-2014 08:27 AM
Project 2013 Report Who Does What When report in Project 2013 Smithy15 Project 1 01-20-2014 08:48 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:50 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft