Uniform units for Total Slack
Is it possible to have total slack displayed in a common unit rather than the one that the duration is entered in?
|
#2
|
|||
|
|||
What common unit are you looking for?
|
#3
|
|||
|
|||
Thanks Julie. I can see that the Total Slack unit is the same as the unit that the Duration has been entered in but I want the Total Slack to be shown in "days" for every task irrespective of what the Duration unit is. Is this possible? and if not, is there a quick way to convert all the Duration values to "days" without manually changing each one?
|
Tags |
display units, total slack |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Total Slack Calculation Incorrect in SubProjects vs MasterPlan | ana | Project | 3 | 05-31-2016 07:58 AM |
Total Slack and Activity with SS Successor only | ketanco | Project | 3 | 05-14-2014 01:59 PM |
total slack of activities and schedule logic | ketanco | Project | 1 | 08-04-2012 05:58 AM |
total slack not changing when changing duration | ketanco | Project | 1 | 02-11-2012 07:23 AM |
Total Slack not updating | damianb | Project | 0 | 06-25-2010 11:48 AM |