tnewton tnewton is offline Assigning resources not shortening task period Windows 7 64bit Assigning resources not shortening task period Office 2013
Novice
Assigning resources not shortening task period
 
Join Date: Apr 2017
Posts: 1
tnewton is on a distinguished road
Default Assigning resources not shortening task period


I have a project that has a duration of 2480 hrs with a start date set. Even though I have four resources at 100% the finish date is approximately 14 months out. It seems Project is only accounting for one person not four. How do I get it to see all four resources working the hours so that the finish date pulls in earlier.
Reply With Quote
  #2  
Old 05-05-2017, 02:36 PM
JulieS JulieS is offline Assigning resources not shortening task period Windows 10 Assigning resources not shortening task period Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

In order for the addition of resources to shorten the task duration, the task needs to be effort driven. Show the task form in the lower pane. It will allow you to easily view status information (Task Type, Effort driven or not) as well as view the work assigned to each resource.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Fixing Work, % of actual work and Final Date in a task (while assigning resources) Campelliann Project 1 01-09-2017 06:15 PM
Assigning resources not shortening task period Assigning Resources and percent complete jwindholz2725 Project 1 02-24-2014 10:56 AM
Assigning resources not shortening task period Assigning Resources to Tasks rickw262 Project 1 01-18-2013 04:46 AM
Assigning resources not shortening task period Assigning calendars to resources automatically david_23 Project 3 03-30-2012 07:43 AM
Assigning resources. Sergey M Project 0 01-25-2006 09:33 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:33 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft