Assigning resources not shortening task period
I have a project that has a duration of 2480 hrs with a start date set. Even though I have four resources at 100% the finish date is approximately 14 months out. It seems Project is only accounting for one person not four. How do I get it to see all four resources working the hours so that the finish date pulls in earlier.
|
|