Old 03-27-2017, 08:19 AM
nicolafusconi nicolafusconi is offline MS Project 2013 - Manually set up the finish date ??? Windows 10 MS Project 2013 - Manually set up the finish date ??? Office 2013
Novice
MS Project 2013 - Manually set up the finish date ???
 
Join Date: Mar 2017
Posts: 1
nicolafusconi is on a distinguished road
Default MS Project 2013 - Manually set up the finish date ???

Hi everyone, I apologize for the stupid question considering that autonomously time ago (at that time I was using MS Project 2010) I had solved the problem. But NOW with MS Project 2013 I cannot find the solution I urgently need.

Scenario:
Start date - April 1
Finish date - April 30


Duration - 60 days

I need to use 60 days as the duration, but I want to set manually the start and finish dates AND avoid automatic calculations by MS Project. MSP 2013 of course because I set up "duration=60 days" then overwrites the finish date April 30 and automatically calculates it as May 30 .
My requirement is: due to the fact that the task is assigned to 2 resources (100% booked for the task) then the agreed duration with the client (60 days) is expected to halve (30 days >>> 1st april>30th april).
Don't know if I'm making a wrong use of MS Project and someone could guide me on how to proceed if there were an approach more brilliant than mine...... BUT If my approach is correct, how can I avoid Project automatically calculating the Finish DATE?

Thanks so much
Reply With Quote
  #2  
Old 03-28-2017, 08:40 AM
JulieS JulieS is offline MS Project 2013 - Manually set up the finish date ??? Windows 10 MS Project 2013 - Manually set up the finish date ??? Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You can have 60 days of Work with two resources but not 60 days of duration between April 1 and April 30.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
MS Project 2013 - Manually set up the finish date ??? New to Project and start and finish keeps adding a minute Bmaez Project 1 10-29-2016 07:17 PM
Project forcing start and finish dates to be the same day daacrusher2001 Project 1 09-28-2016 11:37 AM
Project 2013 - Change GANTT Bar Colour By Main Task Date CaelanT Project 1 02-09-2015 12:50 PM
flag to indicate finish date does not equal baseline finish date TCB Project 3 08-06-2014 02:49 PM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:25 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft