Seftonbarn Seftonbarn is offline Predecessor and successor on different calendar Windows 7 64bit Predecessor and successor on different calendar Office 2007
Novice
Predecessor and successor on different calendar
 
Join Date: Jul 2014
Posts: 2
Seftonbarn is on a distinguished road
Default Predecessor and successor on different calendar

Successor calendar working day is 07:30 to 18:00.
Predecessor calendar working day is 08:00 to 17:00.


How can I get the successor to start the next work day, rather than starting at 17:00 for just one hour after the predecessor has finished.
Reply With Quote
  #2  
Old 03-17-2017, 02:01 AM
JulieS JulieS is offline Predecessor and successor on different calendar Windows 10 Predecessor and successor on different calendar Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm afraid the best option is a work around. Create a task with a duration of one minute - set it as the success to task 1 - predecessor to task to and apply the successor calendar to the task. But, the next question is why are you applying so many task calendars? Give us some more insight into the "whys" and we'll tro to be more helpful.
Reply With Quote
  #3  
Old 03-17-2017, 04:50 AM
Guloluseus Guloluseus is offline Predecessor and successor on different calendar Windows 7 64bit Predecessor and successor on different calendar Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

This is a common problem in many projects I have, (infrastructure construction) where permitted working times vary in different areas (eg road 1 working times are 0800-1800, while road 2 is off peak only due to access, and road 3 is 0900-1730 due to residents). Its not a choice, but imposed by the client.

OP- depending on exactly why the limits are imposed, there may be alternatives. Generally, I will use a standard day and standard night shift, and ignore the stated working times. Use days as your standard time, and this allows you to create a programme where you only use one calendar, but can keep track of work.

In your case, where there is only an hour or so difference between working days, I would suggest this is the best solution. If you need to keep track of the available time for each task, create a column (or columns) for start/ finish times, if only as a record of the permitted times.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Predecessor and successor on different calendar Start date of successor Mountaingoat Project 1 09-19-2015 01:43 PM
Predecessor and successor on different calendar viewing pred and successor after window split ketanco Project 2 06-21-2014 06:17 AM
Total Slack and Activity with SS Successor only ketanco Project 3 05-14-2014 01:59 PM
using a predecessor twice ketanco Project 2 03-07-2014 04:52 PM
Predecessor and successor on different calendar seeing successor information for a task ketanco Project 1 06-02-2012 09:35 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:26 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft