#1
|
|||
|
|||
Help : MS Project 2010
Kindly see the attached file. I am following the PDF tutorial from MSProject 2010, it was good all along but suddenly i cant seem to follow the steps that they are saying.
What's happening : 1. As instructed, i am assigning a Cost on the Task " Author reading and signing at book fair" obviously because the doer of it has no value/amout (the Project file was one of the Practice files included on software) 2. It is said that i must assign "800" on the cost field for "Toni Poe" (he is assigned on the task) as you can see on the Assign Resources dialogue box is says "$0" for Tony on that task. Then the instruction is just simply type "800" on the cost field. But i cannot just type 800 on the cost field and if i double click on it another box appears which is the Resource info box. I am stucked, help guys. |
#2
|
|||
|
|||
The instructions say to assign the 800 cost to the Travel Cost resource, not Toni. The Travel Cost resource must be defined as a cost type resource.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
View issue Project 2010 | mwhittleyt | Project | 2 | 01-15-2015 06:33 PM |
Location of Global.MPT for Project 2010 | OTPM | Project | 1 | 09-18-2014 11:06 AM |
Help with MS Project 2010 | abhishekjethi87 | Project | 3 | 06-04-2014 06:29 AM |
Help with MS Project 2010 | MikeJ | Project | 1 | 01-27-2012 07:36 AM |
Bar chart in Project 2010. | aligahk06 | Project | 0 | 07-04-2010 07:37 AM |