I have a question, and I couldn't search for an answer because I don't know what to search for exactly, but I hope I can give a clear discription of what I need ![]() I have an activity, which is dependable on a previous activity, but its not a Finish to Start... it is a Finish(25%) to Start... can this be done in MS Project? Another question is, can 1 activity start then end, and then start again after a couple of days? Thank you |
|
|