#1
|
|||
|
|||
Newbie in Office Project
I have a question, and I couldn't search for an answer because I don't know what to search for exactly, but I hope I can give a clear discription of what I need
I have an activity, which is dependable on a previous activity, but its not a Finish to Start... it is a Finish(25%) to Start... can this be done in MS Project? Another question is, can 1 activity start then end, and then start again after a couple of days? Thank you |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
[Office]How to create project timeline similar to this? | Coderedpl | Project | 0 | 09-11-2009 01:23 PM |
Connectivity issue of Project Professional with Project Server | kashif | Project | 0 | 03-27-2009 06:37 AM |
Error 9571 when opening Project Server from Project Pro | mona | Project | 0 | 04-24-2007 07:50 AM |
Hello all! Newbie here with a queston | spamh8tr | Outlook | 1 | 11-30-2006 08:04 AM |
Different % complete in Project Center & View a Project | mikaelbelchior | Project | 1 | 01-25-2006 12:56 AM |