Question Newbie in Office Project

I have a question, and I couldn't search for an answer because I don't know what to search for exactly, but I hope I can give a clear discription of what I need

I have an activity, which is dependable on a previous activity, but its not a Finish to Start... it is a Finish(25%) to Start... can this be done in MS Project?



Another question is, can 1 activity start then end, and then start again after a couple of days?

Thank you
Reply With Quote
  #2  
Old 04-13-2010, 09:07 AM
xxsawer xxsawer is offline Newbie in Office Project Windows XP Newbie in Office Project Office 2003
Novice
 
Join Date: Apr 2010
Posts: 21
xxsawer is on a distinguished road
Default

Hi, both is managable...
If you have two tasks, second task should be started when first task is completed of 75%, than set the gap between these two activities to -25%

Sure you can divide some task. I am not sure of English name of that button, but its button on standard toolbar, the name should be something like Divide task. Other option how to do that is to go to the Resource usage view and enter zero days or zero hours in place where you want to divide it...
Reply With Quote
  #3  
Old 04-14-2010, 02:54 AM
wajebwahab wajebwahab is offline Newbie in Office Project Windows Vista Newbie in Office Project Office 2007
Novice
Newbie in Office Project
 
Join Date: Apr 2010
Posts: 4
wajebwahab is on a distinguished road
Default

Thank you

One more question

I type 28 days for a specific task, that starts from 8/8/09 why does the end date say 8/17/09 (its 28 days why is it deducting 11?)

I have my working time from 8 A.M till 8 A.M
Reply With Quote
  #4  
Old 04-14-2010, 01:30 PM
xxsawer xxsawer is offline Newbie in Office Project Windows XP Newbie in Office Project Office 2003
Novice
 
Join Date: Apr 2010
Posts: 21
xxsawer is on a distinguished road
Default

If you are using 24h calendar, that is 24 working hours per day. When you enter 28d as duration of some task it means 28x8 hours, no matter what calendar you are using. If the task you are entering lasts for 28x24 hours than you have to enter something like 28wd (w means whole). I am not sure if the letter 'w' will be correct for your version of MS Project. I am using Czech version of Project and there is letter 'u'. 'w' could be in english version probably...
Reply With Quote
  #5  
Old 04-14-2010, 01:36 PM
wajebwahab wajebwahab is offline Newbie in Office Project Windows Vista Newbie in Office Project Office 2007
Novice
Newbie in Office Project
 
Join Date: Apr 2010
Posts: 4
wajebwahab is on a distinguished road
Default

Alright, I will try this... thank you alot, for all the help... other questions will definately be comming as I'm very new to this...

Thank you all!
Reply With Quote
  #6  
Old 04-14-2010, 01:40 PM
wajebwahab wajebwahab is offline Newbie in Office Project Windows Vista Newbie in Office Project Office 2007
Novice
Newbie in Office Project
 
Join Date: Apr 2010
Posts: 4
wajebwahab is on a distinguished road
Default

ok the only thing that worked for me was ed - elapsed days is it the same?
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
[Office]How to create project timeline similar to this? Coderedpl Project 0 09-11-2009 01:23 PM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM
Newbie in Office Project Hello all! Newbie here with a queston spamh8tr Outlook 1 11-30-2006 08:04 AM
Different % complete in Project Center & View a Project mikaelbelchior Project 1 01-25-2006 12:56 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:04 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft