magnus1982 magnus1982 is offline Task order - dependencys Windows 10 Task order - dependencys Office 2016
Novice
Task order - dependencys
 
Join Date: Mar 2017
Posts: 1
magnus1982 is on a distinguished road
Default Task order - dependencys


Hello.

On the beginning sorry form my English.

I just stared work with MS Project.

My question is :

When i have task A (start on 13.03 and finish on 15.03 -3days ) and task B and i am setting dependency to task A Ms Project automaticity setting start date as 15.03.
I can't understand that . if I set 3days that is 13/14/15 then next task should start automatically at 16.03 not 15.03.

Please help
Reply With Quote
  #2  
Old 03-04-2017, 08:45 AM
JulieS JulieS is offline Task order - dependencys Windows 10 Task order - dependencys Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

My guess is that there is a mis-match between your calendar and your definition of hours per day in Project. Turn on the display of time in File > Options, General. My guess is that you have dropped the definition of "hours per day" to below 8. However, the calendar still allows more than those hours for working time.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Insert SubProject after Task x? (Linking ConsolidateProjects to Task) surumadurum Project 1 04-05-2016 06:09 AM
How to make a task adjust its end date depending on another task? (Newbie) ravl13 Project 3 07-27-2014 06:10 PM
Task order - dependencys Copy and Paste of a Task...Including all of the Task's 'children'...to a new task KRTSTARRYNIGHT Project 1 07-01-2014 06:54 AM
Task order - dependencys Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:51 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft