Task order - dependencys
Hello.
On the beginning sorry form my English. I just stared work with MS Project. My question is : When i have task A (start on 13.03 and finish on 15.03 -3days ) and task B and i am setting dependency to task A Ms Project automaticity setting start date as 15.03. I can't understand that . if I set 3days that is 13/14/15 then next task should start automatically at 16.03 not 15.03. Please help |
#2
|
|||
|
|||
My guess is that there is a mis-match between your calendar and your definition of hours per day in Project. Turn on the display of time in File > Options, General. My guess is that you have dropped the definition of "hours per day" to below 8. However, the calendar still allows more than those hours for working time.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Insert SubProject after Task x? (Linking ConsolidateProjects to Task) | surumadurum | Project | 1 | 04-05-2016 06:09 AM |
How to make a task adjust its end date depending on another task? (Newbie) | ravl13 | Project | 3 | 07-27-2014 06:10 PM |
Copy and Paste of a Task...Including all of the Task's 'children'...to a new task | KRTSTARRYNIGHT | Project | 1 | 07-01-2014 06:54 AM |
Mid-Task resource scheduled 0 hours increasing task duration needlessly | DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |