Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 02-20-2017, 10:19 AM
RichB RichB is offline Resource Reports not showing Sub project Resource group hours Windows 10 Resource Reports not showing Sub project Resource group hours Office 2016
Novice
Resource Reports not showing Sub project Resource group hours
 
Join Date: Feb 2017
Posts: 2
RichB is on a distinguished road
Default Resource Reports not showing Sub project Resource group hours




I need to create a report that shows “work” or “remaining work” across time at a resource group level. The visual report works correctly on each individual project (as per image 1). I have created a master template & assigned several sub projects to this.

However when trying to view the cumulative hours across a resource group across sub projects in a master, I am unable to create the report when filtered on the relevant level. (image 3)
The number of hours that appears in the field “Remaining Work” is correct at a Resource Group level – ie – it adds the hours per resource within the relevant resource group. Plus when broken down a resource level, the hrs are shown (image 2)

However when I filter this over time, at a group level no hours are calculated?

I have tried using a Resource Pool & by just using a master Document & copying the resource names each time, so the naming conventions are common, both show the correct figures, but when they are filtered at a task level in the sub project version – the data is blank?

Thank you for your help
Attached Images
File Type: jpg Image 1.JPG (83.2 KB, 16 views)
File Type: jpg Image 2.JPG (87.4 KB, 16 views)
File Type: jpg Image 3.JPG (101.3 KB, 16 views)
Reply With Quote
  #2  
Old 02-21-2017, 10:57 AM
JulieS JulieS is offline Resource Reports not showing Sub project Resource group hours Windows 10 Resource Reports not showing Sub project Resource group hours Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Is the resource pool connnect to the subproject? If you are using a pool, it needs to be connected to the subproject files and not the master project. You should be reporting from the Resource Pool file.
Reply With Quote
  #3  
Old 02-22-2017, 06:34 AM
RichB RichB is offline Resource Reports not showing Sub project Resource group hours Windows 10 Resource Reports not showing Sub project Resource group hours Office 2016
Novice
Resource Reports not showing Sub project Resource group hours
 
Join Date: Feb 2017
Posts: 2
RichB is on a distinguished road
Default

yes the resource pools are linked, but I wasn't running the report from the Resource Pool. I was running from the master doc, so I think that has done it!

Thank you for your help
Reply With Quote
  #4  
Old 02-24-2017, 08:55 AM
JulieS JulieS is offline Resource Reports not showing Sub project Resource group hours Windows 10 Resource Reports not showing Sub project Resource group hours Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Great. Let us know if you have any further questions.
Reply With Quote
Reply

Tags
resource groups, sub projects

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Fixed Hours for Resource Planning ebilbrough Project 1 12-28-2016 11:47 AM
Resource Reports not showing Sub project Resource group hours Project 2013 - Issue with Resource Usage showing wrong dates michaelwex Project 1 02-11-2016 08:41 AM
Resource Reports not showing Sub project Resource group hours Seperate Cost per Resource Group and Taskname Emanol Espina Project 6 12-17-2015 02:59 PM
Resource Reports not showing Sub project Resource group hours Resource not getting enough hours allocated to them, therefore extending duration joday48 Project 1 08-01-2014 08:54 AM
Resource Reports not showing Sub project Resource group hours Gantt bar text labels - possible to put resource hours against the bars? mtbtomo Project 5 05-14-2014 01:18 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:47 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft