Hi,

I have problem with my MS Project 2010. In my project I have 2 positions:

1. First Meeting
...
...
...
2. The day of party

I know that the day of party is 1.09.2017 - this date I will write manually. I want the date of "The day of party" to set automatically as 24 month before the date of "First Meeting".

Anybody knows what should I do?

Regards,
Piotr
Reply With Quote
  #2  
Old 02-17-2017, 09:39 AM
JulieS JulieS is offline Automatic adjustment date Windows 10 Automatic adjustment date Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm not sure I follow. You know the Day of Party but the first meeting should be 2 years before. You're going to set it manually - I am guessing through a constraint. But then you say the day of the party should be scheduled 24 months before. I think what you are asking is for a Start to Finish relationship with a 104 week (I would not use month) lead. The Day of Party is the predecessor and its start drives the finish of the first meeting.
Reply With Quote
  #3  
Old 02-28-2017, 05:00 AM
zbiku25 zbiku25 is offline Automatic adjustment date Windows 7 64bit Automatic adjustment date Office 2010 64bit
Novice
Automatic adjustment date
 
Join Date: Feb 2017
Posts: 2
zbiku25 is on a distinguished road
Default

Thank you very much indeed! It helps

Best regards,
Piotr

Quote:
Originally Posted by JulieS View Post
I'm not sure I follow. You know the Day of Party but the first meeting should be 2 years before. You're going to set it manually - I am guessing through a constraint. But then you say the day of the party should be scheduled 24 months before. I think what you are asking is for a Start to Finish relationship with a 104 week (I would not use month) lead. The Day of Party is the predecessor and its start drives the finish of the first meeting.
Reply With Quote
  #4  
Old 02-28-2017, 09:03 AM
JulieS JulieS is offline Automatic adjustment date Windows 10 Automatic adjustment date Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Great. Thanks for the feedback.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Automatic adjustment date Office 2016 for Mac keeps getting the wrong date for the automatic date susanto_tm Word 10 11-05-2018 05:41 AM
Automatic adjustment date Stop Automatic Date-Update janetb Word 10 11-10-2016 12:05 AM
Automatic adjustment date Table adjustment on Surface OneNote TheMax OneNote 1 01-23-2015 04:33 PM
Automatic adjustment date Automatic date updates. WLVanS Word 12 01-29-2011 04:01 AM
Automatic Date Change Marusja Word 0 03-04-2009 03:45 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:05 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft