This time I am looking for a way of restricting the splitting of tasks on a task level when leveling.
I am aware of the general setting in the leveling options but was wondering if there is a way of restricting certain tasks to be split when leveling? |
#2
|
|||
|
|||
![]()
Add the field "Leveling Can split" to the table and set the field to "no" for tasks you do not want split.
|
#3
|
|||
|
|||
![]()
There you go! Julie to the rescue once again.
All these columns, all these settings... Need to extend my desk to make room for another monitor. I dont suppose this setting is available on creation of a task? |
#4
|
|||
|
|||
![]()
No, but keep the field in a view and set it as needed.
|
#5
|
|||
|
|||
![]()
Thank you Julie for another good advice!
|
#6
|
|||
|
|||
![]()
You're welcome and thanks for the feedback.
|
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Task split between two resources, but not equal effort | pmgreen | Project | 1 | 09-04-2014 05:22 PM |
![]() |
KRTSTARRYNIGHT | Project | 1 | 07-01-2014 06:54 AM |
![]() |
proj | Project | 1 | 01-13-2012 08:38 AM |
Split a task | fridos | Project | 2 | 05-30-2011 11:19 AM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |