OTPM OTPM is offline Manage external task dependencies Windows 10 Manage external task dependencies Office 2016
Expert
Manage external task dependencies
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default Manage external task dependencies


Hi All

I have a large number of projects with external dependencies. However the challenge I have is how to ensure all those links always link to the correct activity in the dependent plan.

For example I have an external dependency in Plan 2 from Plan 1. However after creating the dependency Plan 2 has 10 new activities added "before" the dependent task ID in Plan 2. This makes my original external dependency link point to the wrong Task ID in Plan 2. I would be interested to hear how others manage this issue.
I have a potential VBA solution to this but would welcome views from other users before I go down this road.

Look forward to receiving responses.

Thanks

Tony
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Manage external task dependencies Copy and Paste of a Task...Including all of the Task's 'children'...to a new task KRTSTARRYNIGHT Project 1 07-01-2014 06:54 AM
single task with combine SS and FF dependencies Blobb Project 3 06-04-2014 12:24 PM
Cross Project Dependencies OTPM Project 6 01-18-2014 07:52 AM
Filter indirect dependencies SirPercival Project 1 07-04-2012 01:03 PM
Impossible task: sort email to external folder billzinn Outlook 1 07-26-2011 06:25 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:46 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft