Not A PMP, but need help
Hello,
So I use MS Project to plan and track various projects I work on for a municipality. I do not however use the program to track "resources", rather I have fixed costs for various stages, such as Design, Permitting, Construction. the questions is what is the best way to set a baseline for these, and then add change order costs within each of these as the project progresses? Thank you. |
#2
|
|||
|
|||
Not to worry that you're not a PMP. Neither am I - just a heavy user of MS Project.
You can manually enter costs against tasks. Save the baseline and then update Actual costs. |
#3
|
|||
|
|||
Thank you Julie for your response. I will give that a try.
|