Old 02-14-2017, 03:48 AM
Mattias Mattias is offline Filter out completed tasks in a report Windows 10 Filter out completed tasks in a report Office 2016
Advanced Beginner
Filter out completed tasks in a report
 
Join Date: Jan 2017
Posts: 34
Mattias is on a distinguished road
Default Filter out completed tasks in a report

I am playing around with a simple report to create a report for a gentleman within the company who really loves his todo-lists...



I have created a simple table where I show
- Project
- Name (of task)
- StartDate
- EndDate
- Resources allocated
- Duration

This table is then filtered on the gentleman in question and this produces a nifty, simple todo

The thing that puzzles me is that in this list I can see prior tasks, already completed and I can not find a way to add an additional filter, to set table to only show future dates.
The other way would of course be to somhow exlude tasks marked as 100% complete, but this one eludes me too...

Any takers?
Reply With Quote
  #2  
Old 02-14-2017, 05:12 AM
JulieS JulieS is offline Filter out completed tasks in a report Windows 10 Filter out completed tasks in a report Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Add the % complete field to the table and use the autofilters (drop down to the right of the field name) to filter out tasks where % complete is 100%.

Using the autofilter allows you to filter on multiple columns on the fly.
Reply With Quote
  #3  
Old 02-14-2017, 06:29 AM
Mattias Mattias is offline Filter out completed tasks in a report Windows 10 Filter out completed tasks in a report Office 2016
Advanced Beginner
Filter out completed tasks in a report
 
Join Date: Jan 2017
Posts: 34
Mattias is on a distinguished road
Default

I am not sure if we are talking about the same view here.
In Gannt view I have the option to filter the column as you describe.

When in Report view, I cannot see any filter option per table column? Not even in the field list.

I forgot to mention that the gentleman in question also loves his todo-lists printed...
Reply With Quote
  #4  
Old 02-14-2017, 04:25 PM
JulieS JulieS is offline Filter out completed tasks in a report Windows 10 Filter out completed tasks in a report Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Ah, sorry. You can create a custom task filter where
Resource Names contain "gentlemans name"
AND
Percent complete does not equal 100

The filter can then apply the filter to the report.
Reply With Quote
  #5  
Old 02-16-2017, 02:36 AM
Mattias Mattias is offline Filter out completed tasks in a report Windows 10 Filter out completed tasks in a report Office 2016
Advanced Beginner
Filter out completed tasks in a report
 
Join Date: Jan 2017
Posts: 34
Mattias is on a distinguished road
Default

Worked like a charm, the only thing that made me go hmmm, was the fact that you apparently cant edit a created filter from the report view.
Reply With Quote
  #6  
Old 02-17-2017, 09:46 AM
JulieS JulieS is offline Filter out completed tasks in a report Windows 10 Filter out completed tasks in a report Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You are correct, the filters can be applied but not edited in the report view. Pop back to a task view and edit away.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to show the overdue, Late, Onschedule & Completed tasks using MSP 2010 AK04 Project 2 01-10-2016 06:35 PM
Filter out completed tasks in a report To Do List Report (Project 2007) Displays Completed Tasks SusanK Project 5 04-23-2014 07:12 AM
Filter out completed tasks in a report Change font colour when tasks are completed meileetan Project 3 09-12-2012 07:09 AM
updating not completed tasks or 0% tasks ketanco Project 3 08-24-2012 05:59 AM
Outlook completed tasks synced with Windows Mobile 6.5 ghumdinger Outlook 0 07-03-2011 07:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:05 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft