#5
|
|||
|
|||
![]()
Things are a bit muddled. Is Task A the predecessor to Task B? In the predecessor field for task B exactly what does it say?
If Task A is the predecessor for B and the relationship is SS+4days, then task B should begin on Tuesday not Monday. The lag counts Thursday, Friday, Saturday, Monday and the task starts on Tuesday.Lag (the +4 days) only counts working time. When Task A starts should have no relationship to Task B. What is the predecessor to Task A? |
|
![]() |
||||