Total work effort for sub tasks
 
Join Date: Feb 2017
Posts: 1
Shaz01 is on a distinguished road
Default Total work effort for sub tasks

Hi all. I have a bunch of child tasks that all have a work effort estimate assigned in man days. These all roll into parent tasks that do not have a priority. You can have different priority child tasks within a parent task.



I have created a new text field called 'Priority' and have assigned a number 1, 2 or 3 against each child task.

All I am looking to do is filter on that Priority field and see the total Work Effort of those child priority tasks combined.

I can't currently do this as a child task rolls up into parent task, and so Work Effort reflects the parent task (not assigned a priority) AND the child task (assigned a priority).

Thoughts please!
Reply With Quote
  #2  
Old 02-01-2017, 10:26 AM
JulieS JulieS is offline Total work effort for sub tasks Windows 7 64bit Total work effort for sub tasks Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You'll need to create a group to group by the priority to see the totals. Generally, you don't assign resources (and work) to summary tasks (parent). The parent task should be the sum of the subtasks.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Scheduling Chained Work Effort with Unchained Work Effort Starkweather Project 1 05-24-2014 12:37 PM
Total work effort for sub tasks Hyperlinks in tasks work differently Jennifer Murphy Outlook 1 03-07-2014 07:54 AM
Total work effort for sub tasks Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Evgeny Project 3 01-03-2013 06:45 AM
Work calculated differently for two seemingly identical tasks SteveD Project 0 10-12-2011 02:05 PM
Duration changes fail to update work effort Panteledes Project 6 05-25-2010 02:27 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:39 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft