![]() |
#1
|
|||
|
|||
![]()
Hi all. I have a bunch of child tasks that all have a work effort estimate assigned in man days. These all roll into parent tasks that do not have a priority. You can have different priority child tasks within a parent task.
I have created a new text field called 'Priority' and have assigned a number 1, 2 or 3 against each child task. All I am looking to do is filter on that Priority field and see the total Work Effort of those child priority tasks combined. I can't currently do this as a child task rolls up into parent task, and so Work Effort reflects the parent task (not assigned a priority) AND the child task (assigned a priority). Thoughts please! |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Scheduling Chained Work Effort with Unchained Work Effort | Starkweather | Project | 1 | 05-24-2014 12:37 PM |
![]() |
Jennifer Murphy | Outlook | 1 | 03-07-2014 07:54 AM |
![]() |
Evgeny | Project | 3 | 01-03-2013 06:45 AM |
Work calculated differently for two seemingly identical tasks | SteveD | Project | 0 | 10-12-2011 02:05 PM |
Duration changes fail to update work effort | Panteledes | Project | 6 | 05-25-2010 02:27 PM |