Old 01-25-2017, 07:03 AM
Pmacdaddy Pmacdaddy is offline Showing a Task Start Date Slip Windows 7 64bit Showing a Task Start Date Slip Office 2010 64bit
Novice
Showing a Task Start Date Slip
 
Join Date: Apr 2012
Location: Cincinnati, OH
Posts: 7
Pmacdaddy is on a distinguished road
Question Showing a Task Start Date Slip

For starters, I have MS Project 2010....
Question - I have laid in the rough elements/tasks for a new, and still very fluid Project. Most of the individual tasks are not linked to any other tasks at this point because of the fact that it is so fluid. Wouldn't make any sense and would be a waste of effort...
With that said however, I want to essentially "lock in" the dates for all of these tasks as they were originally provided by all of the participants of the Project. I need this so that when Party "B" later advises the projected start date of their action has slipped 2 weeks, I will be able to show the original "soft" commit date and now the new date.
All of the tasks are inter-related, but not yet linked in MS Project. They will eventually be linked up once everything settles down - but I need any change in projected date be visually/readily identifiable to all Participants so that they can readily discern for themselves that a change in date has occurred in one of the Project tasks.
How do I do that?
Thanks.....
Reply With Quote
  #2  
Old 01-26-2017, 10:14 AM
JulieS JulieS is offline Showing a Task Start Date Slip Windows 7 64bit Showing a Task Start Date Slip Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

One option is to save a baseline. You can then compare the baseline data against the current data. Start and Finish Variance are already calculated for you. Once everyting is set - you can save a new baseline and then again get to see variance.

You really can "lock" dates - only use either baselines or spare date fields to show the difference between what was promised and what was delivered.
Reply With Quote
Reply

Tags
slip, task slip

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Set start and end dates of one task based on one other task only zamshabeer Project 1 07-07-2016 11:25 AM
Showing a Task Start Date Slip Start date of successor task does not change raminraiszadeh Project 3 09-19-2015 01:41 PM
Showing a Task Start Date Slip Showing how much work is required to complete a project according to summary task start/end times PDX-ADM-TRM01 Project 1 03-30-2015 04:05 PM
How to make a task adjust its end date depending on another task? (Newbie) ravl13 Project 3 07-27-2014 06:10 PM
Task with Start date but no Due date? bplat Outlook 0 01-12-2012 08:10 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:56 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft