Hi,



i have planed a project. Now i will assign some resources(Workers) to the specifics process.

With the assign i have some question and i hope u can help me...

I have a process Duration 100 days, Work 100h
If i put 1 resource on this process ms project shared the whole work over this 100 days.
Put i want that my resource works the first 5 days 40h then in the middle 20h and the last 5 days 40h.
How i can tell ms project when the resource must done his works?

i hope u understanding what i mean ;-)

thx...
Reply With Quote
  #2  
Old 01-20-2017, 06:38 PM
Guloluseus Guloluseus is offline Planing Resources Windows 7 64bit Planing Resources Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

I would suggest that you make 3 new tasks (call them part 1, part 2, part 3 if you like) and assign work to these as 40 hrs, 20 hrs and 40 hrs (see pic below) and add a resource.
Then set each task to "Fixed Work" (double click on the task and see pic for the pop up box). You can then set the duration to 1 wk at the beginning and end, and 80 days to the mid section (as pic) to give a duration of 100 days. This will give the effect you want.

I asume that this is a task that carried through, if it a weeks work then a gap, more work, gap, and a final weeks work, please let us know as this has an easier solution.

NOTE picture is an attachment.

Hope It helps.
Attached Images
File Type: jpg example.JPG (119.0 KB, 16 views)
Reply With Quote
  #3  
Old 01-26-2017, 11:53 AM
JulieS JulieS is offline Planing Resources Windows 7 64bit Planing Resources Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Quote:
Originally Posted by flownfluid View Post
Hi,

i have planed a project. Now i will assign some resources(Workers) to the specifics process.

With the assign i have some question and i hope u can help me...

I have a process Duration 100 days, Work 100h
If i put 1 resource on this process ms project shared the whole work over this 100 days.
Put i want that my resource works the first 5 days 40h then in the middle 20h and the last 5 days 40h.
How i can tell ms project when the resource must done his works?

i hope u understanding what i mean ;-)

thx...
You can edit the spread of work in the Resource Usage view.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Planing Resources Leveling Resources Help! Mthomas88 Project 1 09-25-2015 08:25 AM
Planing Resources Certain Resources Not Leveling PDX-ADM-TRM01 Project 1 04-27-2015 03:45 PM
Even allocation of resources craigsmillie Project 3 08-26-2014 03:10 AM
Planing Resources Resources - only allow users to select from resources pool grazi Project 1 04-04-2014 11:12 AM
Assigning resources. Sergey M Project 0 01-25-2006 09:33 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:54 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft