Planing Resources
Hi,
i have planed a project. Now i will assign some resources(Workers) to the specifics process. With the assign i have some question and i hope u can help me... I have a process Duration 100 days, Work 100h If i put 1 resource on this process ms project shared the whole work over this 100 days. Put i want that my resource works the first 5 days 40h then in the middle 20h and the last 5 days 40h. How i can tell ms project when the resource must done his works? i hope u understanding what i mean ;-) thx... |
#2
|
|||
|
|||
I would suggest that you make 3 new tasks (call them part 1, part 2, part 3 if you like) and assign work to these as 40 hrs, 20 hrs and 40 hrs (see pic below) and add a resource.
Then set each task to "Fixed Work" (double click on the task and see pic for the pop up box). You can then set the duration to 1 wk at the beginning and end, and 80 days to the mid section (as pic) to give a duration of 100 days. This will give the effect you want. I asume that this is a task that carried through, if it a weeks work then a gap, more work, gap, and a final weeks work, please let us know as this has an easier solution. NOTE picture is an attachment. Hope It helps. |
#3
|
|||
|
|||
Quote:
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Leveling Resources Help! | Mthomas88 | Project | 1 | 09-25-2015 08:25 AM |
Certain Resources Not Leveling | PDX-ADM-TRM01 | Project | 1 | 04-27-2015 03:45 PM |
Even allocation of resources | craigsmillie | Project | 3 | 08-26-2014 03:10 AM |
Resources - only allow users to select from resources pool | grazi | Project | 1 | 04-04-2014 11:12 AM |
Assigning resources. | Sergey M | Project | 0 | 01-25-2006 09:33 AM |