Question physical % complete

hi - hope someone can telll me:
I have a project with work loaded say 10000 hrs over a duration over a few years.


When I progress the plan with Physical % complete over a month period say 2%. The value in actual work hrs is different to that when I divide the 10000hrs by the 2%. Any reason why?
Reply With Quote
  #2  
Old 01-11-2017, 06:38 PM
JulieS JulieS is offline physical % complete Windows 7 64bit physical % complete Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi Andy,

Unless the work is progressing at an even pace throughout the entire project, the % complete - which is a duration measure - will not equal the % work complete. For example in the beginning of a project you may not have as many hours expended in each month as you may have later in the project when more resources join. So, you may have progressed 2% of the total duration, but because of backloaded resources, you have not consumed 2% of the total work. Look a the task usage view, add work to the timescaled portion zoom out and look at your work load per month.
Reply With Quote
  #3  
Old 01-11-2017, 11:03 PM
Andy Francis Andy Francis is offline physical % complete Windows 8 physical % complete Office 2003
Novice
physical % complete
 
Join Date: Jul 2013
Posts: 6
Andy Francis is on a distinguished road
Default physical % complete

Hi Julie, we are using a standard Level of Effort ( as a rule of credit) for the activity. What i cant fathom out is if I have loaded the work hrs for the project duration 10000. I have then progressed the phys % from 0 to 2%. I would of expected the actual No of hrs to = 1000/2% = 200 hrs. what the actual is showing me is 196hrs. which is giving me a false EVM calcuation.
Reply With Quote
  #4  
Old 01-16-2017, 05:36 PM
JulieS JulieS is offline physical % complete Windows 7 64bit physical % complete Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm not sure that the Physical % complete ties in with actual work values. The Earned Value is either calculated from % complete (duration) or physical % complete - but not % work complete. When I create a simple project and set things up to use Physical % complete as the earned value method (both the field and the calculation), updating Physical % complete has no effect on Actual Work. The actual work values remain zero.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
physical % complete How to show planned% complete and actual% complete on the (Project Overview) dashboard report? zislam14 Project 3 12-17-2015 03:03 PM
physical % complete physical complete %, regular work, vs % complete ketanco Project 1 06-16-2014 11:08 AM
Physical % Complete and Task Duration ChuckM Project 3 02-09-2014 09:21 AM
physical % complete project for projected vs physical theWizardAKQ Project 3 01-24-2014 06:16 AM
physical % complete complete % and physical complete % ketanco Project 3 05-25-2012 08:19 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:33 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft