Question physical % complete

hi - hope someone can telll me:
I have a project with work loaded say 10000 hrs over a duration over a few years.


When I progress the plan with Physical % complete over a month period say 2%. The value in actual work hrs is different to that when I divide the 10000hrs by the 2%. Any reason why?
Reply With Quote
  #2  
Old 01-11-2017, 06:38 PM
JulieS JulieS is offline physical % complete Windows 7 64bit physical % complete Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi Andy,

Unless the work is progressing at an even pace throughout the entire project, the % complete - which is a duration measure - will not equal the % work complete. For example in the beginning of a project you may not have as many hours expended in each month as you may have later in the project when more resources join. So, you may have progressed 2% of the total duration, but because of backloaded resources, you have not consumed 2% of the total work. Look a the task usage view, add work to the timescaled portion zoom out and look at your work load per month.
Reply With Quote
  #3  
Old 01-11-2017, 11:03 PM
Andy Francis Andy Francis is offline physical % complete Windows 8 physical % complete Office 2003
Novice
physical % complete
 
Join Date: Jul 2013
Posts: 6
Andy Francis is on a distinguished road
Default physical % complete

Hi Julie, we are using a standard Level of Effort ( as a rule of credit) for the activity. What i cant fathom out is if I have loaded the work hrs for the project duration 10000. I have then progressed the phys % from 0 to 2%. I would of expected the actual No of hrs to = 1000/2% = 200 hrs. what the actual is showing me is 196hrs. which is giving me a false EVM calcuation.
Reply With Quote
  #4  
Old 01-16-2017, 05:36 PM
JulieS JulieS is offline physical % complete Windows 7 64bit physical % complete Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm not sure that the Physical % complete ties in with actual work values. The Earned Value is either calculated from % complete (duration) or physical % complete - but not % work complete. When I create a simple project and set things up to use Physical % complete as the earned value method (both the field and the calculation), updating Physical % complete has no effect on Actual Work. The actual work values remain zero.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
physical % complete How to show planned% complete and actual% complete on the (Project Overview) dashboard report? zislam14 Project 3 12-17-2015 03:03 PM
physical % complete physical complete %, regular work, vs % complete ketanco Project 1 06-16-2014 11:08 AM
Physical % Complete and Task Duration ChuckM Project 3 02-09-2014 09:21 AM
physical % complete project for projected vs physical theWizardAKQ Project 3 01-24-2014 06:16 AM
physical % complete complete % and physical complete % ketanco Project 3 05-25-2012 08:19 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:41 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft