Project does not distribute work evenly between the days
Hi,
I have an over allocated resource, in the resource sheet project sometimes distributes evenly between the days the remaining amount of work, but then in the last day the value is completely diferrent for example. 9, 9 , 9 , 20 (h). Why does this happen? Thanks in advance, |
#2
|
|||
|
|||
Is the task Fixed Duration? Does the resource have a special working calendar? Is the task manually scheduled?
|
|