JulieS JulieS is offline Project does not distribute work evenly between the days Windows 7 64bit Project does not distribute work evenly between the days Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Is the task Fixed Duration? Does the resource have a special working calendar? Is the task manually scheduled?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
VBA to distribute all columns evenly within tables NorthSuffolk Word VBA 3 09-23-2017 05:28 PM
Calculating 6.5hr work days altja Project 3 02-10-2014 03:11 PM
12 hour work days (shifts) John Franklin Project 22 11-12-2013 03:19 PM
Project Days mah_dahshan Project 1 12-17-2012 04:27 AM
Calendar work days in advance paol:o Outlook 4 05-27-2012 07:23 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:57 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft