anderskile anderskile is offline How do I get a higher priority task to interupt when required resource becomes available? Windows 10 How do I get a higher priority task to interupt when required resource becomes available? Office 2013
Novice
How do I get a higher priority task to interupt when required resource becomes available?
 
Join Date: Jan 2017
Posts: 1
anderskile is on a distinguished road
Default How do I get a higher priority task to interupt when required resource becomes available?

Hi,



I'm a complete newbie to MS Project, but somehow I've ended up with a fairly complex project, with hundreds of tasks and 40 or so resources. Lot's of interdependencies. The project deadline is sharp, needs to end by end of June.

Automated leveling is not working, the project just ends up way past deadline. Manual levelling is really, really confusing and difficult. I'm allowed to add new resources to the project if needed ( though with a bit of management conflict). But I notice there's a lot of resource slack, that I should take better advantage of. However, I can't seem to get resources to "fill in available time" to a secondary task. I can get them to work on multiple tasks, by carefully adjusting the percentage. But this kind of manual adjustment is way to difficult in the real life project.

I've added a sample project, to illustrate my point. The sample doesn't demonstrate the leveling issue fully, since no resources are overallocated.



What I want, off course, is for resource Res1 to abort his progress on LowPriTask, complete the work that needs to be done on HighPriTask, (so Res2 can get to work on LateTask), then go back and complete LowPriTask. This would cut the project timeline by 1 week.

I hope my sample project demonstrate the problem, since understanding the real life project will be a bit complex.

sample.mpp

br
Anders
Attached Images
File Type: png Capture2.PNG (20.7 KB, 11 views)
Reply With Quote
  #2  
Old 01-09-2017, 06:06 PM
JulieS JulieS is offline How do I get a higher priority task to interupt when required resource becomes available? Windows 7 64bit How do I get a higher priority task to interupt when required resource becomes available? Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Are you actually applying different priorities to the tasks and then using the leveling option for Priority/Standard? Are you allowing Project to split tasks?
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How do I get a higher priority task to interupt when required resource becomes available? Showing how much work is required to complete a project according to summary task start/end times PDX-ADM-TRM01 Project 1 03-30-2015 04:05 PM
How do I get a higher priority task to interupt when required resource becomes available? Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
How do I get a higher priority task to interupt when required resource becomes available? Two resource sheet for one task zapco76 Project 1 11-20-2012 05:43 AM
How do I get a higher priority task to interupt when required resource becomes available? Task allocation by priority dlowrey Excel Programming 3 06-18-2012 07:24 PM
Calender month view peeve - display high priority over low priority appts? ghumdinger Outlook 0 07-25-2011 03:56 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:37 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft