Less productive resources in %alocation
 
Join Date: Jan 2017
Posts: 6
Campelliann is on a distinguished road
Default Less productive resources in %alocation

Hi,



I have in MS Project the Resource John with availability 100%, I have a second resource Ann which is a junior working together with John which is supposed to produce 1/5 of John (20%).

When I assign these resources to a task, I would like that the daily number hours of work of John is 5 times greater than Ann. So if a task requires 6 hours of work per day, I want 5 to be of John.

The percentage of availability does give a greater amount of hours to John, but still doesn't work fully.

I am working with fixed work/fixed duration tasks. So if I increase work time, I want project to recalculate the percentage of allocation to each of the resources, maintaining the final date.

Any help?

Thanks,

C
Reply With Quote
  #2  
Old 01-09-2017, 06:09 PM
JulieS JulieS is offline Less productive resources in %alocation Windows 7 64bit Less productive resources in %alocation Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I am not sure what you mean by "still doesn't work fully". They key issue is making sure that task is effort driven. Assign John and enter total work. Then assign Ann.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Less productive resources in %alocation Leveling Resources Help! Mthomas88 Project 1 09-25-2015 08:25 AM
Making my outlook more productive ljstevens Outlook 1 08-26-2015 11:42 PM
Less productive resources in %alocation Certain Resources Not Leveling PDX-ADM-TRM01 Project 1 04-27-2015 03:45 PM
Less productive resources in %alocation Resources - only allow users to select from resources pool grazi Project 1 04-04-2014 11:12 AM
Assigning resources. Sergey M Project 0 01-25-2006 09:33 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:45 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft