Guloluseus Guloluseus is offline Is MSProject suitable for a large amount of projects? Windows 7 64bit Is MSProject suitable for a large amount of projects? Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

In terms of tasks MSP can cope with, I regularly produce programmes with 600-1200 tasks. The largest was about 5-6000 tasks, with an addition near the end of around 1200 snags (so 6-7000 tasks in all), and it handled it fine. So yes, project can deal with large programmes

For your example, I would suggest that using 1 programme would be simplest. Each individual project can be added under its own summary bar, and would remove the need for task resourcing at a deeper level.

I would also go with Julies suggestion of finding a good course. I was self taught and it was a struggle for the first few years, although it does mean you have a good understanding of what you are doing.
Don't go for a generla planning course- these tend to be for project managers (allegedly) and dont have enough detail to make them worth the effort. Best case is to find a planner that can spare the time, and get a quick run through of the basics, then return when you find yourself out of your depth. there is no substitute for experience; MS Project is not simple, and someone showing you what to do is worth its weight.
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Most suitable Office application for linking Technical Documents JJG2 Office 0 05-30-2016 01:21 AM
Is MSProject suitable for a large amount of projects? MSProject 2013 - making two12 hr shifts/day derek112 Project 7 08-03-2014 05:39 PM
A graph for large amount of data CD2005 Excel 5 05-01-2014 04:51 AM
Is MSProject suitable for a large amount of projects? Large amount of text as a form field. JustK Word 2 11-15-2011 11:17 AM
Is there a way to change the header in a large amount of documents at one time? ntsstaffing Word 1 07-11-2009 12:12 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:53 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft