Old 12-26-2016, 11:42 AM
Wocky Wocky is offline Auto Levelling Resource Does something I don't understand Windows 7 64bit Auto Levelling Resource Does something I don't understand Office 2010 64bit
Novice
Auto Levelling Resource Does something I don't understand
 
Join Date: Dec 2016
Posts: 8
Wocky is on a distinguished road
Default Auto Levelling Resource Does something I don't understand


Dear,

Can someone help me understand what MS Project does when I click on the level all button?

In attachment I have a msproject file.
When I click on the "Resource/Level/Level All"-button it splits the task on row 11.
I can understand that this happens, but what I don't understand is that msproject actually still over-allocates the resource "Montage" whit the task on row 5.

So in my opinion the resource "Monteren" is still over-allocated on "Tue 27/12".
Can someone please help me understand?

Thanks in advance.
(my apologies for bad English).
Wocky
Attached Files
File Type: mpp Project1.mpp (477.0 KB, 9 views)
File Type: mpp Project2.mpp (381.0 KB, 9 views)
Reply With Quote
  #2  
Old 12-28-2016, 11:44 AM
JulieS JulieS is offline Auto Levelling Resource Does something I don't understand Windows 7 64bit Auto Levelling Resource Does something I don't understand Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

What are your leveling options? Day by Day? Allow delays to critical tasks? Take a look at the Resource Usage view and add the Peak Units field to the view.
Reply With Quote
  #3  
Old 12-28-2016, 05:48 PM
Wocky Wocky is offline Auto Levelling Resource Does something I don't understand Windows 7 64bit Auto Levelling Resource Does something I don't understand Office 2010 64bit
Novice
Auto Levelling Resource Does something I don't understand
 
Join Date: Dec 2016
Posts: 8
Wocky is on a distinguished road
Default

Hi,

Thanks for your response.
Uhm.. In the levelling options I marked "day by day".
I just don't understand why "montage" is being planned at the same time, in 2 different tasks...

Ah.. I see a peak 200% yes.. but I don't want it to be able to peak.

Do you know how to turn it of?

Thanks in advance.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Auto Levelling Resource Does something I don't understand #REF! Error that I cannot seem to understand krispykreme Excel Programming 5 09-11-2016 11:25 PM
Auto Levelling Resource Does something I don't understand MS Project Resource Capacity and Auto-levelling Senor_Babs Project 2 11-01-2014 02:46 PM
Auto Levelling Resource Does something I don't understand Trying to understand formulas and error Jack-P-Winner Excel 1 04-22-2014 03:50 PM
Auto Levelling Resource Does something I don't understand Levelling resource's units to calculate duration task codeghi Project 10 03-01-2014 08:13 AM
Auto Levelling Resource Does something I don't understand MS Project - Maximizing resource levelling aguatorito Project 3 03-10-2013 06:08 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:58 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft