MS Project 2010 copy & paste
How do I copy tasks from one MPP file to another MPP without losing the dependencies?
If I lose the dependencies, I have a lot of manual work to create those dependencies again MS Project 2010 Thank you |
#2
|
|||
|
|||
Select the tasks by row number and then copy/paste. That should preserve any link relationships.
|