Hi,



I'm about to work with a new client whose working time each day varies - its fair to say their working hours are non-standard as below.

Monday is 8am to 5pm
Tues to Thurs is 7am to 5pm
Friday is 7am to 3pm

Before I start to work them I've been thinking about how I could accurate capture duration data on projects plans that we will be developing going forward.

Its a given that I need to align the settings in the 'Calendar options for this project' with the project calendar, otherwise durations and work estimates could be wrong or inaccurate.

So, given this non-standard shift pattern, how best should I reflect the working hours in the calendar options to ensure symmetry between the two.

Thanks in advance for your help.
Reply With Quote
  #2  
Old 11-30-2016, 07:36 AM
JulieS JulieS is offline Project Calendar - working days have varying hours Windows 7 64bit Project Calendar - working days have varying hours Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You are correct that you only get to define a "day" and a "week" once. i would still likely work with a day = 8hrs and a week = 40hrs as the hours do add to 40. As long as you have set the working calendar (Change working time) correctly, it should still schedule fine. If you enter a two day duration task that starts Tuesday morning at 7:00 am, it will finish 16 working hours later.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Project Calendar - working days have varying hours Calculate Average Time Elapsed in Days, hours and minutes Nina46 Excel 9 09-11-2015 02:09 AM
My emails don't come into Outlook 2013 for hours or even days after they are accessable via Yahoo Annie1 Outlook 0 08-20-2014 10:16 AM
showing calendar days by keeping normal workday calendar ketanco Project 11 11-01-2013 08:27 AM
Project Calendar - working days have varying hours Calculate difference by days and hours alysolyman Excel 6 05-13-2013 02:19 AM
Project Calendar - working days have varying hours calendar -reduced working hours pm_newbie Project 7 01-17-2012 10:34 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:13 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft