Adding Hours in MS Project with Picture
Hello Community
I need help with adding hours in MS Project. Is it possible? And if, how? Check the pic below. Thank you for your help! |
#2
|
|||
|
|||
I'm afraid I don't understand. Adding hours where? Are you talking about tracking actual work?
|
#3
|
|||
|
|||
Is it possible to sum up the highlightet hours? Like it is in excel?
|
#4
|
|||
|
|||
If that is the work field, display the Project Summary task and it will show the sum of the work. On the Gantt Chart Tools Ribbon, click the checkbox to display the project summary task.
|
#5
|
|||
|
|||
Quote:
The Project summary task shows me the needed time from beginning to the end. What id like to see is the summary of the needed hours, is this possible? |
#6
|
|||
|
|||
Abit fuzzy with your terminology, is "needed hours" the same as duration?
|
#7
|
|||
|
|||
If you add a summary task above the tasks you want to add, and then indent, you'll see the sum of the subtasks.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Adding of times total to be in hours | jen0dorf | Excel | 4 | 06-20-2014 11:53 PM |
Project Hours | Mav | Project | 4 | 03-07-2014 04:47 PM |
Hours in MS Project Changed | ayeh | Project | 14 | 02-12-2014 10:41 AM |
MS Project-timescale in hours | John Franklin | Project | 5 | 10-30-2013 08:41 AM |
Powerpoint automatically changing picture size when adding a picture (2010) | One_Life | PowerPoint | 7 | 01-20-2012 06:57 AM |