jaywizz1 jaywizz1 is offline Creating a task similar to Working Time exceptions Windows 7 64bit Creating a task similar to Working Time exceptions Office 2010 32bit
Novice
Creating a task similar to Working Time exceptions
 
Join Date: Mar 2016
Posts: 2
jaywizz1 is on a distinguished road
Default Creating a task similar to Working Time exceptions

Folks I have a project that for a period of 2 weeks there are a range of activities that I cannot undertake but there are some that my team can be getting on with.



Ordinarily I'd add a Work Exception to prevent any tasks being scheduled but this is not practical in this instance.

So I have simply scheduled a single task to block out 2 weeks and then attached some tasks to this manually. This works in general but when the schedule starts to move I then have to go back through the entire task list and tweak which tasks are now related to this blocked out time and which tasks have had this relation nullified.

Has anyone any ideas?
Reply With Quote
  #2  
Old 11-04-2016, 10:30 AM
JulieS JulieS is offline Creating a task similar to Working Time exceptions Windows 7 64bit Creating a task similar to Working Time exceptions Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Create a task calendar that sets non-working time for the two weeks. Assign it to the tasks that cannot be worked on. If the two week window changes, change the task calendar.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Creating a task similar to Working Time exceptions Need help with modifying a replacing font VBA code- similar task but subtle change kissingfrogs2003 Word VBA 3 08-30-2016 11:42 AM
Word Autocorrect exceptions not working. Spotofpaint Word 0 10-23-2014 06:14 PM
Autocorrect Exceptions not working danvdr Word 6 05-26-2014 09:37 PM
Creating a task similar to Working Time exceptions Creating Similar Versions of Same Document that Auto-Update harrisate Word 1 03-07-2014 08:59 PM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:14 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft