Planned vs actual
I'm looking for advice in setting up a scenario:
|
#2
|
|||
|
|||
Create the task and the person. Assign the resource at 50% and enter 20 hours of work. Project will calculate 1 week duration.
Save a baseline to capture the "plan". You can then enter 30 hours of actual work and project will mark the task 100% complete and extend the duration to allow 30 hours of work in 60 hour duration. So, did they do the 30 hours of work within a week? If so, switch to the Task Usage view and enter the 30 hours in actual work in the time-phased portion to end after one week. |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
How to show planned% complete and actual% complete on the (Project Overview) dashboard report? | zislam14 | Project | 3 | 12-17-2015 03:03 PM |
Planned Against Actual MSP 2010 | leesc84 | Project | 5 | 02-02-2015 08:51 AM |
Microsoft Project Managing Planned / Earned Value & Actual Costs | shane_dav71 | Project | 1 | 10-06-2014 06:07 PM |
Planned Versus Actual Completion | abw1987 | Project | 8 | 12-04-2011 11:50 AM |
Very simple / STUPID question about actual vs. planned hours | sam-sam | Project | 0 | 12-07-2010 02:55 PM |