#1
|
|||
|
|||
Create a calendar based on shifts not days
Where I work we set our tasks on a project schedule based on a duration of shifts not days. I am trying to figure out how to get this to work and to reflect proper time frames for follow on work as the schedule code is changed.
Example: a 1-0 calendar is one 8 hr shift 7 days a week without regards to holidays a 1-5 calendar is one 8 hr shift 5 days a week (Mon-Fri) no holidays a 1-6 calendar is one 8 hr shifts 6 days a week (Mon-Sat) no holidays a 2-5 calendar is two 8 hr shift 5 days a week (Mon-Fri) a 2-6 calendar is two 8 hr shifts 6 days a week (Mon-Sat) a 3-0 calendar is three 8 hr shift 7 days a week without regards to holidays Thanks in advance for help in solving this issue. |
#2
|
|||
|
|||
I don't follow exactly. The duration of the tasks vary or do the start and finish of the tasks vary. I would suggest the following. Express the duration in days where 1 day = 8 hours. You can define multiple calendars with the different working configurations. Then add the task calendar column and change the task calendar to reflect which "shift" is going to perform the task. The duration will stay the same but the finish date will change depending upon the definition of the calendar.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
12 hour work days (shifts) | John Franklin | Project | 22 | 11-12-2013 03:19 PM |
12 shifts/7 days | John Franklin | Project | 1 | 11-11-2013 09:11 AM |
showing calendar days by keeping normal workday calendar | ketanco | Project | 11 | 11-01-2013 08:27 AM |
Calendars, 12 hr shifts, 24 hrs/ 7 days | John Franklin | Project | 3 | 10-30-2013 08:16 AM |
calendar for rotating shifts | dude1 | Excel | 0 | 05-29-2011 01:58 PM |