![]() |
#1
|
|||
|
|||
![]()
Where I work we set our tasks on a project schedule based on a duration of shifts not days. I am trying to figure out how to get this to work and to reflect proper time frames for follow on work as the schedule code is changed.
Example: a 1-0 calendar is one 8 hr shift 7 days a week without regards to holidays a 1-5 calendar is one 8 hr shift 5 days a week (Mon-Fri) no holidays a 1-6 calendar is one 8 hr shifts 6 days a week (Mon-Sat) no holidays a 2-5 calendar is two 8 hr shift 5 days a week (Mon-Fri) a 2-6 calendar is two 8 hr shifts 6 days a week (Mon-Sat) a 3-0 calendar is three 8 hr shift 7 days a week without regards to holidays Thanks in advance for help in solving this issue. |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
12 hour work days (shifts) | John Franklin | Project | 22 | 11-12-2013 03:19 PM |
12 shifts/7 days | John Franklin | Project | 1 | 11-11-2013 09:11 AM |
showing calendar days by keeping normal workday calendar | ketanco | Project | 11 | 11-01-2013 08:27 AM |
![]() |
John Franklin | Project | 3 | 10-30-2013 08:16 AM |
calendar for rotating shifts | dude1 | Excel | 0 | 05-29-2011 01:58 PM |