Old 10-10-2016, 12:27 PM
stanleysamuel stanleysamuel is offline Project Status and Overdue tasks Windows 7 64bit Project Status and Overdue tasks Office 2013
Novice
Project Status and Overdue tasks
 
Join Date: Oct 2016
Posts: 1
stanleysamuel is on a distinguished road
Default Project Status and Overdue tasks

I am trying to generate a report on overdue tasks.

(a) The project plan has been rebaselined 3 times. If I run the late tasks report from MSP, will it use the last rebaselined plan as reference or something else to run the late report?
(b) The project status date. I understand I can use the current date to generate a late tasks report. However, is it more meaningful to generate tasks with the current rebaselined plan's Go Live date as the project status date? What I am trying to get is that we need to know all the tasks that are delayed in the project, due to the current delays. How do I get that?
Reply With Quote
  #2  
Old 10-12-2016, 11:32 AM
JulieS JulieS is offline Project Status and Overdue tasks Windows 7 64bit Project Status and Overdue tasks Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Quote:
Originally Posted by stanleysamuel View Post
I am trying to generate a report on overdue tasks.

(a) The project plan has been rebaselined 3 times. If I run the late tasks report from MSP, will it use the last rebaselined plan as reference or something else to run the late report?
The late Tasks Report uses the status date, not the baseline dates. It is built off the Status field. The status field will show complete, On Schedule, Late, or future task. A task is late if "the timephased cumulative percent complete does nto reach midnight on the day before the status date." If you want to know how you are performing against a baseline - look at the Variance table - it will show Start and Finish Variance.

Quote:
Originally Posted by stanleysamuel View Post
(b) The project status date. I understand I can use the current date to generate a late tasks report. However, is it more meaningful to generate tasks with the current rebaselined plan's Go Live date as the project status date? What I am trying to get is that we need to know all the tasks that are delayed in the project, due to the current delays. How do I get that?
Again - look at variance information. You can build your own report to shows Start and Finish Variance as well as duration and work variance to paint a more complete picture.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to show the overdue, Late, Onschedule & Completed tasks using MSP 2010 AK04 Project 2 01-10-2016 06:35 PM
Project Status and Overdue tasks Project Status and Late Tasks - Incorrect BarryB Project 4 08-02-2015 01:50 PM
RAG Status on Project 2013 deepsk Project 3 04-23-2015 07:26 AM
How to show overdue tasks? Anastasia Sudbinina Project 1 03-17-2015 08:26 AM
How to modify send status report in tasks office 2010 jonyorker Outlook 0 03-03-2015 07:31 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:50 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft