Project Status and Overdue tasks
I am trying to generate a report on overdue tasks.
(a) The project plan has been rebaselined 3 times. If I run the late tasks report from MSP, will it use the last rebaselined plan as reference or something else to run the late report? (b) The project status date. I understand I can use the current date to generate a late tasks report. However, is it more meaningful to generate tasks with the current rebaselined plan's Go Live date as the project status date? What I am trying to get is that we need to know all the tasks that are delayed in the project, due to the current delays. How do I get that? |
#2
|
|||
|
|||
Quote:
Quote:
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
How to show the overdue, Late, Onschedule & Completed tasks using MSP 2010 | AK04 | Project | 2 | 01-10-2016 06:35 PM |
Project Status and Late Tasks - Incorrect | BarryB | Project | 4 | 08-02-2015 01:50 PM |
RAG Status on Project 2013 | deepsk | Project | 3 | 04-23-2015 07:26 AM |
How to show overdue tasks? | Anastasia Sudbinina | Project | 1 | 03-17-2015 08:26 AM |
How to modify send status report in tasks office 2010 | jonyorker | Outlook | 0 | 03-03-2015 07:31 AM |