jkdiesel jkdiesel is offline Rollup of mulitple sub tasks and non-working days Windows 7 64bit Rollup of mulitple sub tasks and non-working days Office 2013
Novice
Rollup of mulitple sub tasks and non-working days
 
Join Date: May 2016
Posts: 11
jkdiesel is on a distinguished road
Default Rollup of mulitple sub tasks and non-working days

I have a basic project set up with multiple levels of sub tasks under one summary tasks. (see photo attached). The thing I cant figure out is this:



using 168004 (green summary task) as an example, I have one project (a 91 day) that started and finished in January 2016. Another project (pmi support) started in july. How can I make the green summary task ONLY show the total days I actually worked, and not the total span from the start of the first one to the end of the second one.
Attached Images
File Type: png untitled.png (49.5 KB, 12 views)
Reply With Quote
  #2  
Old 09-27-2016, 01:48 PM
Guloluseus Guloluseus is offline Rollup of mulitple sub tasks and non-working days Windows 7 64bit Rollup of mulitple sub tasks and non-working days Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

the simple answer is that if you want to keep your current programme, you cannot. A summary bar is just that;a summary. It starts on the first day under it and finishes on the last one. Any gaps or non working time dont matter.

If you are happy to change the layout, you can make another summary task at the same level as the 168004 one and give it a new name. this would then separate out the 2 projects as separate. as far as I know, thats pretty much te only options.
Reply With Quote
  #3  
Old 09-28-2016, 11:36 AM
JulieS JulieS is offline Rollup of mulitple sub tasks and non-working days Windows 7 64bit Rollup of mulitple sub tasks and non-working days Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Quote:
Originally Posted by jkdiesel View Post
I have a basic project set up with multiple levels of sub tasks under one summary tasks. (see photo attached). The thing I cant figure out is this:

using 168004 (green summary task) as an example, I have one project (a 91 day) that started and finished in January 2016. Another project (pmi support) started in july. How can I make the green summary task ONLY show the total days I actually worked, and not the total span from the start of the first one to the end of the second one.
Have you considered showing the Work field to show much work was actually accomplished during the duration? As you have discovered Duration <> Work. The duration counts the number of working days between the start of the earliest subtask to the end of the latest subtask. You can have a situation where there are large gaps between subtasks that will be reflected in the summary task duration. However, the work for the subtasks will be summarized correctly.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
conflicting tasks with exception days damokaa Project 1 04-05-2016 06:11 AM
Rollup of mulitple sub tasks and non-working days reminder for every 15 working days araamuthan Outlook 1 03-25-2015 11:49 PM
reminder for every 15 working days araamuthan Excel 0 03-25-2015 06:49 AM
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM
Rollup of mulitple sub tasks and non-working days Non-Working Days on Gantt JayTT Project 1 01-28-2011 05:42 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:44 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft